Sunday, 15/09/2024

Notice to Mariners

The construction: dredging and maintenance of Port and the water flow used for cooling turbine of Duyen Hai Electric Power Center in 2024 phase 1

 NOTICE TO MARINERS

The construction: dredging and maintenance of Port and the water flow used for cooling turbine of Duyen Hai Electric Power Center in 2024 phase 1

 No. 77/TBHH-TCTBĐATHHMN dated April 04th, 2024

TVH – 15 – 2024

Waters: Tra Vinh Province.

Fairway:  used for large load ships entry and exit of Hau River.

 

VMS-South would like to inform that the establishment of  The construction of dredging and maintenance of Port and the water flow used for cooling turbine of Duyen Hai Electric Power Center in 2024 phase 1 with the following content:

1-The construction of dredging and maintenance:

- Site: Sea Port Area of Duyen Hai Electric Power Center, Dan Thanh Commune, Duyen Hai District, Tra Vinh Province.

- Range: The private Flow, turning basin, The water flow used for cooling DH1 and DH3 Plants; The water flow used for cooling DH3RM Plant and DH2 – Sea Port Area of Duyen Hai Electric Power Center, the position of controlling range points following the below coordinates table:

No. Points VN-2000 WGS-84
Latitude Longitude Latitude Longitude
1 Private Flow
1.1 C1 09˚34’23,43″N 106˚32’10,04″E 09˚34’19,76″N 106˚32’16,44″E
1.2 C2 09˚34’12,31″N 106˚32’00,13″E 09˚34’08,65″N 106˚32’06,54″E
1.3 C3 09˚33’26,46″N 106˚32’02,88″E 09˚33’22,80″N 106˚32’09,29″E
1.4 P3 09˚34’25,05″N 106˚32’08,19″E 09˚34’21,38″N 106˚32’14,60″E
1.5 P4 09˚34’10,27″N 106˚31’55,03″E 09˚34’06,61″N 106˚32’01,44″E
1.6 P5 09˚33’58,25″N 106˚31’47,30″E 09˚33’54,58″N 106˚31’53,71″E
1.7 P6 09˚33’42,70″N 106˚31’48,23″E 09˚33’39,03″N 106˚31’54,64″E
1.8 T5 09˚34’21,81″N 106˚32’11,88″E 09˚34’18,15″N 106˚32’18,29″E
1.9 T6 09˚34’10,70″N 106˚32’01,98″E 09˚34’07,03″N 106˚32’08,38″E
1.10 T7 09˚34’06,40″N 106˚31’59,45″E 09˚34’02,73″N 106˚32’05,86″E
1.11 T8 09˚33’54,06″N 106˚31’55,76″E 09˚33’50,39″N 106˚32’02,17″E
1.12 T9 09˚33’43,18″N 106˚31’56,41″E 09˚33’39,51″N 106˚32’02,82″E
1.13 T10 09˚33’28,29″N 106˚32’04,52″E 09˚33’24,62″N 106˚32’10,92″E
2 Turning basin
2.1 P3 09˚34’25,05″N 106˚32’08,19″E 09˚34’21,38″N 106˚32’14,60″E
2.2 T5 09˚34’21,81″N 106˚32’11,88″E 09˚34’18,15″N 106˚32’18,29″E
2.3 T4 09˚34’24,80″N 106˚32’14,54″E 09˚34’21,14″N 106˚32’20,95″E
2.4 T3 09˚34’27,06″N 106˚32’21,93″E 09˚34’23,39″N 106˚32’28,34″E
2.5 T2 09˚34’29,89″N 106˚32’24,45″E 09˚34’26,22″N 106˚32’30,86″E
2.6 T1 09˚34’34,80″N 106˚32’24,60″E 09˚34’31,13″N 106˚32’31,00″E
2.7 P1 09˚34’40,48″N 106˚32’18,12″E 09˚34’36,81″N 106˚32’24,53″E
2.8 P2 09˚34’31,14″N 106˚32’09,80″E 09˚34’27,47″N 106˚32’16,21″E
2.9 C1 09˚34’23,43″N 106˚32’10,04″E 09˚34’19,76″N 106˚32’16,44″E
3 The water flow used for cooling the DH1&DH3 plant
3.1 A1 09˚34’53,60″N 106˚31’39,39″E 09˚34’49,93″N 106˚31’45,79″E
3.2 A2 09˚34’29,02″N 106˚32’07,40″E 09˚34’25,36″N 106˚32’13,81″E
3.3 A3 09˚34’52,06″N 106˚31’40,16″E 09˚34’48,39″N 106˚31’46,56″E
3.4 A4 09˚34’53,03″N 106˚31’41,02″E 09˚34’49,37″N 106˚31’47,43″E
3.5 A7 09˚34’29,51″N 106˚32’07,83″E 09˚34’25,85″N 106˚32’14,24″E
3.6 A8 09˚34’28,54″N 106˚32’06,96″E 09˚34’24,87″N 106˚32’13,37″E
4 The water flow used for cooling the DH3MR&DH2 plant
4.1 C1 09˚35’11,29″N 106˚31’55,70″E 09˚35’07,63″N 106˚32’02,11″E
4.2 C2 09˚35’10,21″N 106˚31’56,93″E 09˚35’06,54″N 106˚32’03,34″E
4.3 C3 09˚35’08,19″N 106˚31’56,87″E 09˚35’04,53″N 106˚32’03,27″E
4.4 C4 09˚34’47,24″N 106˚32’13,56″E 09˚34’43,57″N 106˚32’19,97″E
4.5 C5 09˚34’46,23″N 106˚32’12,27″E 09˚34’42,57″N 106˚32’18,68″E
4.6 C6 09˚35’09,02″N 106˚31’54,11″E 09˚35’05,36″N 106˚32’00,52″E
4.7 M1 09˚35’09,54″N 106˚31’55,28″E 09˚35’05,87″N 106˚32’01,69″E
4.8 M2 09˚35’07,51″N 106˚31’56,36″E 09˚35’03,85″N 106˚32’02,77″E
4.9 M3 09˚34’46,74″N 106˚32’12,91″E 09˚34’43,07″N 106˚32’19,32″E
4.10 M4 09˚34’39,91″N 106˚32’17,63″E 09˚34’36,24″N 106˚32’24,04″E
4.11 P1 09˚34’40,48″N 106˚32’18,12″E 09˚34’36,81″N 106˚32’24,53″E
4.12 W13 09˚34’39,34″N 106˚32’17,14″E 09˚34’35,68″N 106˚32’23,54″E

2- Dumping ground for waste Area:

- Position: Out at Sea of Dan Thanh Commune, Duyen Hai District, Tra Vinh Province.

- Area: the position of controlling range points following the below coordinates table:

No. Points VN-2000 WGS-84
Latitude Longitude Latitude Longitude
1 P4.1 09°27’17,60″ 106°38’08,86″ 09˚27’13,93″N 106˚38’15,26″E
2 P4.2 09°26’14,69″ 106°39’21,96″ 09˚26’11,03″N 106˚39’28,36″E
3 P4.3 09°25’00,41″ 106°38’15,21″ 09˚24’56,74″N 106˚38’21,62″E
4 P4.4 09°26’05,00″ 106°37’02,30″ 09˚26’01,33″N 106˚37’08,70″E

3- Means and Time for construction:

- Means: Trailing suction hopper dredger, Excavator, bottom discharge barge, Tugboat, Canoe and pump dredger.

- Time: Estimated 117 days, starting from April 1, 2024.

 

NAVIGATION GUIDANCE

 

All vessels navigating on the fairway used for large load ships entry and exit of Hau River and Sea area with coordinates mentioned above, pay attention to crossing through the area that means are executing for dredging and maintenance along the joyney route to dump  ground for waste of  Trailing suction hopper dredgers and the position of the Dumping ground for waste Area mentioned above for keep watching, ensuring smoothly communication and absolutely comply with the appointment of Maritime Administration of Can Tho, the regulation force at the site and the implementation of avoiding collision with means mentioned above following rules at the site for maritime safety.

For further information, please contact directly to Thermal Power Project 3 PMU./.([1])

([1]) Tổ chức cung cấp số liệu, thông tin phục vụ việc công bố thông báo hàng hải chịu trách nhiệm trước pháp luật về sự chính xác của số liệu, thông tin mình cung cấp theo khoản 3, điều 47, Nghị định số 58/2017/NĐ-CP.


Other notice

Depth of shallow sections in Ganh Rai Bay, from buoy “71” to Beacon “83”, turning basin VQ01 on Sai Gon-Vung Tau fairway in 2015

(Vietnamese) Về thông số kỹ thuật các khu neo đậu tàu trên sông Hậu thuộc vùng nước cảng biển do Cảng vụ Hàng hải Cần Thơ quản lý

The area of ​​surveying and repairing underground equipment on the sea floor in the Lan Tay – Lan Do mine area, lot 06.1 offshore of Ba Ria – Vung Tau province

Depth of wharf 30.000DWT (wharf B5) in Go Dau B port

New establishment of specialized buoys “H1”, “H2”, “H3” that marking warning of anchoring area Hon Mot belongs to Vinpearl Nha Trang tourism vessel project