Friday, 22/10/2021

Notice to Mariners

Construction area of ​​dredging area in in digging hole and add mooring floating 85000T at Ba Son factory

NOTICE TO MARINERS

Construction area of ​​dredging area in in digging hole and add mooring floating 85000T at Ba Son factory

No.195/TBHH-TCTBĐATHHMN dated November 8, 2017

VTU - 45 - 2017

Waters: Bà Rịa – Vũng Tàu province.

Fairway:  Vũng Tàu – Thị Vải.

VMS-South would like to inform that: Project 9 Dept of General Industries Millitary will carry out dredging work in digging hole and add mooring floating 85000T at Ba Son factory as follows:

  1. The coordinates of working areas in front of the wharf are coordinates
Points VN-2000 WGS-84
Latitude (j) Longitude (l) Latitude (j) Longitude (l)
A1 10032’58,14” N 107001’23,93” E 10032’54,47” N 107001’30,38” E
A 2 10032’57,34” N 107001’23,09” E 10032’53,67” N 107001’29,54” E
A3 10032’53,70” N 107001’26,61” E 10032’50,02” N 107001’33,06” E
A4 10032’54,50” N 107001’27,45” E 10032’50,82” N 107001’33,90” E

 ( The coordinates is Project 9 Dept of General Industries Millitary supply)

  1. Equipments list:
Number Equiments ID number
1 Bucket hook HP 4500
2 Mud tank HP 3469
3 Mud tank SG 7946
4 Mud tank HP 4378
5 Tug LA 03803
  1. Working time: until to 31/12/2017
  • NAVIGATION GUIDANCE:

All means navigating on Vung Tau – Thi Vai fairway, crossing execution area mentioned above, should pay attention to reducing speed, to enhance lookouts and communicate with execution unit at the site by VHF for maritime safety.


Other notice

(Vietnamese) Về việc chấm dứt hoạt động phao báo hiệu chuyên dùng “P1”, “P2” phục vụ thi công nạo vét luồng Soài Rạp

New establishment of special buoys for execution of waters in front of Port, Turning Basin, Building Terry Port, wharf, Vinh Tan Inland waterway port

Depth of waters in front of Tan Cang – Hiep Phuoc terminal

Specifications on the depth of the fairway at Ben Dam Port – Con Dao

Depth of waters in front of DONG XUYEN PORT JSC