NOTICE TO MARINERS
The construction area of the project to upgrade AtoN system of the fairway used for large load ships entry of Hau River
No. 19/TBHH-TCTBĐATHHMN dated 23 January, 2024
TVH – 01 – 2024
Waters: Tra Vinh Province
Fairway: used for large load ships entry of Hau River
VMS-South would like to inform that the construction area of the project to upgrade AtoN system of the fairway used for large load ships entry of Hau River with the following details:
- The construction area: Along two sides of fairway’s edges used for large load ships entry of Hau River, Duyen Hai district, Tra Vinh province.
2. Estimated time for construction: From January 23, 2024 to February 27, 2024.
3. The characteristics of execution means:
- Name of vessel: M/V VT 0311;
- Nationallity: Việt Nam;
- Dimension: Total lenght: 29,16 m; Width: 11,0 m; Draught: 1,6 m;
- Call sign: 3WGL;
- Administrative registration number: SG-OTH-002176-2;
- IMO: 09026576;
- Ship’s class: VR042199.
NAVIGATION GUIDANCE
All vessels navigating on the fairway used for large load ships entry of Hau River, pay attention to keep safety distance of M/V VT0311 vessel with characteristics mentioned above for maritime safety, absolutely obey with the guidance of Maritime Administration of Can Tho, the maritime force, the regulations unit at the site and performance of avoiding collision with the construction means following rules for maritime safety./. ([1])