Friday, 22/10/2021

Notice to Mariners

Construction area of ​​dredging area in front of the wharf, construction of wharf and boat wharf – Warehousing Investment Project – general Hoa Sinh Vam Co Dong port

NOTICE TO MARINERS

Construction area of ​​dredging area in front of the wharf, construction of wharf and boat wharf  Warehousing Investment Project - general  Hoa Sinh Vam Co Dong port

No.189/TBHH-TCTBĐATHHMN dated November 3, 2017

ĐNA  –  04 – 2017.

Waters: Đồng Nai province.

Fairway: Sài Gòn – Vũng Tàu

VMS-South would like to inform that:

Hoa Sinh Vam Co Dong joint-stock company will carry out dredging works in front of the wharf, constructing wharf and dock wharf – General port and Warehousing Investment Project, as follows

  1. The coordinates of the dredging areas in front of the wharf are coordinates
Points  VN-2000  WGS-84
Latitude (j) Longitude (l) Latitude (j) Longitude (l)
N1 10039’36,7” N 106048’16,8” E 10039’33,0” N 106048’23,2” E
N2 10039’41,3” N 106048’08,8” E 10039’37,6” N 106048’15,2” E
N3 10039’43,8” N 106048’10,3” E 10039’40,1” N 106048’16,7” E
N4 10039’39,2” N 106048’18,3” E 10039’35,5” N 106048’24,7” E

 ( The coordinates is Hoa Sinh Vam co Dong company supply)

  1. Working time: 06 months (from 10/2017 to 04/2018)
  2. Equipments list:
Number Equipments ID number
1 Khánh Giang 5 Suction dredger SG.5264
2 Khánh Giang 17 Suction dredger SG.7895
3 Barges piling TG.15148
4 Tug barge TG.18578
5 Barges piling TG.24678
6 Tug barge TG.14797

 

 

 

NAVIGATION GUIDANCE:

All means navigating on fairway, crossing execution area mentioned above, should pay attention to reducing speed, to enhance lookouts and communicate with execution unit at the site by VHF for maritime safety.


Other notice

Depth after dredging from the middle of fairway TC2 to turning basin of Quy Nhon fairway 2014

New establishment of AtoN system for specialized fairway to Duyen Hai Thermal Power Plants, Tra Vinh Province

Depth of waters in front of ​​5,000 DWT wharf – Thanh Le petroleum port

182/TBHH-TCTBĐATHHMN – The AAG Segment 1H cable system repairing construction site on offshore sea of Ba Ria – Vung Tau province.

Completion of salvage and relocation of sunk SG 8193 barge on Soai rap fairway