NOTICE TO MARINERS

Depth of waters of fairway for huge vessels go in Hau river 2021, section sea fairway and Tat canal

No. 208/TBHH-TCTBĐATHHMN dated September 26, 2022

TVH – 24 – 2022.

Waters: Tra Vinh province

Fairway:  For huge vessels go in Hau river

VMS-South would like to inform:

Within surveyed fairway the dredging design is maintained by fairway and the Tat canal belong to fairway for huge vessels go in Hau river, limited and guided by AtoN system, the width of 70 m:

- Section from sea fairway: from the area adjacent to the general fairway to buoy No. “7” + 235 m, a length of about 1.2 km, a depth of 6.56 m

- Section Tat canal:

+ From beacon No. “13” – 07 m to beacon No.“13” + 16 m, the length is 23 m, the depth is 6,72 m.

+ From beacon No. “15” + 600 m to beacon No. “17” – 150 m, the length is 900 m, the depth is 6,50 m.

+ From beacon No. “22” – 570 m to beacon No. “22” + 390 m, the length is 960 m, the depth is 6,50 m.

NAVIGATION GUIDANCE:

All means navigating on the fairway for huge vessels go in Hau river, Soai Rap, pay attention to buoy mentioned above, navigating following the fairway center, the guidance of AtoN system, keep smoothly communication, and absolutely comply with the appointment of Maritime Administration of Can Tho.


Other notice

Termination of special marks “C1”, “C2” belongs to petro store K34/Department of Logistics/District 9 (period 1) – List: quay station, wharf 5.000DWT and dredging

Termination of “KS2″ buoy’s operation on fairway for large load vessels in and out of Hau River

Parameters depth of waters in front of wharf 5.000 DWT and barge Terminal – Vinh Long port Terminal of VĨNH LONG PORT JOINT STOCK COMPANY