Thursday, 20/03/2025

Notice to Mariners

Depth of waters in Anchorage area, Turning basin area and Dương Dong Hoa Phu fairway

NOTICE TO MARINERS

Depth of waters in Anchorage area, Turning basin area and Dương Dong Hoa Phu fairway

No. 171/TBHH-TCTBĐATHHMN dated August 02, 2023

BTN – 10 – 2023

Waters: Binh Thuan province.

VMS-South would like to inform that Depth of waters in Anchorage area, Turning basin area and Dương Dong Hoa Phu fairway:

  1. Within surveyed waters in area No. 1 – Anchorage area:
 Point VN-2000 WGS-84
Latitude Longitude Latitude Longitude
B1 11°08’25,3”N 108°32’37,5”E 11°08’21,6”N 108°32’43,9”E
B2 11°08’22,7”N 108°32’41,0”E 11°08’19,0”N 108°32’47,4”E
B3 11°08’17,1”N 108°32’36,4”E 11°08’13,4”N 108°32’42,8”E
B4 11°08’19,6”N 108°32’33,2”E 11°08’15,9”N 108°32’39,6”E

The depth is determined by a 200kHz-frequency reverb to from Datum Chart is 7,80 m.

  1. Within surveyed waters in area No. 2 – Turning basin area:
 Point VN-2000 WGS-84
Latitude Longitude Latitude Longitude
C1 11°07’59,9”N 108°32’46,2”E 11°07’56,2”N 108°32’52,6”E
C2 11°08’07,3”N 108°32’47,2”E 11°08’03,6”N 108°32’53,7”E
C3 11°08’14,4”N 108°32’53,4”E 11°08’10,7”N 108°32’59,9”E
C4 11°08’22,9”N 108°32’49,5”E 11°08’19,2”N 108°32’56,0”E
C5 11°08’22,9”N 108°32’40,7”E 11°08’19,2”N 108°32’47,1”E
C6 11°08’17,3”N 108°32’36,1”E 11°08’13,6”N 108°32’42,6”E
C7 11°08’05,4”N 108°32’39,6”E 11°08’01,7”N 108°32’46,0”E

The depth is determined by a 200kHz-frequency reverb to from Datum Chart is 7,59 m.

  1. Within surveyed waters in area No. 3 – the fairway into Anchorage area and wharf:
 Point VN-2000 WGS-84
Latitude Longitude Latitude Longitude
L01 11°07’05,9”N 108°33’46,0”E 11°07’02,2”N 108°33’52,5”E
L02 11°07’08,4”N 108°33’48,2”E 11°07’04,7”N 108°33’54,6”E
L03’ 11°08’38,7”N 108°31’59,5”E 11°08’35,0”N 108°32’05,9”E
L04’ 11°08’36,2”N 108°31’57,4”E 11°08’32,5”N 108°32’03,8”E

The depth is determined by a 200kHz-frequency reverb to from Datum Chart is 6,16 m.

Data based on chart symbols from BVBP01 to BPBV03 and from BV01 to BV04, ratio 1/1000 was measured by Quang Minh Waterway Transportation Construction Consultant Company Limited completed in July, 2023.

Furthermore information contact to Pacific Petroleum Transport And Logistic Joint Stock Company.


Other notice

Completing the recovery of the overturned vehicle VNL 02 on the waters of Ninh Thuan province

New establishment of 03 the buoys “SR1”, “SR2”, “BP” serving construction works: Dredging and maintaining the Soai Rap fairway in 2021

Depth of waters for large tonnage vessels in Hau river

New establishment of specialized buoys “A1”, “A2” that marking construction area of ​​Ca Mau wind power plant 1A

(Vietnamese) Về khu vực chuyên dùng: Diễn tập ứng cứu tràn dầu trên vùng biển Vũng Tàu