Within range of designed fairway’s bottom is 100 m wide, the section from buoys no. “0” to “16” of Dinh An – Sông Hậu fairway is 18,7 km long, depth is determined by Echo sounding frequency 200 kHz to Chart Datum “0” as follows:

  1. The section from buoys no. “0” to “1” + 990 m, is 2,7 km long, depth is 3,0 m.
  2. The section from buoys no. “1” + 990 m to “4A” + 450 m, is 2,5 km long, depth is 0,8 m.
  3. The section from buoys no. “4A” + 450 m to “6A” – 340 m, is 2,6 km long, depth is 2,0 m.
  4. The section from buoys no. “6A” – 340 m to “6A” – 44 m, is 300 m long, depth is 1,8 m.
  5. The section from buoys no. “6A” – 44 m to “10” – 410 m, is 2,2 km long, depth is 2,0 m.
  6. The section from buoys no. “10” – 410 m to “10” + 180 m, is 590 m long, depth is 1,6 m is closed on the starboard side of fairway, depth at fairway center is 1,9 m.
  7. The section from buoys no. “10” + 180 m to “9” – 200 m, is 750 m long, depth is 2,1 m.
  8. The section from buoys no. “9” – 200 m to “12” – 376 m, is 1,0 km long, depth is 3,1 m.
  9. The section from buoys no. “12” – 376 m to “16”, is 6,1 km long, depth is 4,0 m.

NAVIGATION GUIDANCE

All means navigating on Dinh An-Song Hau fairway, the section fairway from buoys no. “0” to “16” is based on The notice to mariners, Paper chart, sounding chart and Aton system for maritime safety. Pay attention to comply with appointment of Maritime Administration of Can Tho./.

SIGN ON BEHALF OF DIRECTOR GENERAL

DEPUTY DIRECTOR GENERAL

(Signed and Sealed)

Đinh Thái Công


Other notice

(Vietnamese) Độ sâu vùng nước trước Cảng Quốc tế SP-PSA – sông Thị Vải­­

Suspending the operation of Bo De Lighthouse

Depth of anchorage, transit area No. 1, 2 and 3 in Van Phong Bay, Khanh Hoa Province

Surveying and clearing obstacles caused by the incident of the Vietsun Integrity ship sank on Saigon – Vung Tau fairway

Depth of shallow sections on Soai Rap fairway (section from Hiep Phuoc industrial turning basin to Binh Khanh conflux)