NOTICE TO MARINERS

Maritime operation of M/V Nile River vessel to serve execution of Nam Con Son 2 gas pipeline Project

No.42 /TBHH-TCTBĐATHHMN dated March 30 ,2020

VTU – 13 – 2020

Waters: Ba Ria-Vung Tau Province.

VMS-South would like to inform that:

  1. The M/V Nile River vessel will conduct to dig and fill Dike to execute Nam Con Son 2 gas pipeline Project, following the straight line with coordinates as follows:
Point WGS-84
Latitude (j) Longitude (l)
KP 324 10022’11,6541”N 107015’13,1651”E
KP 207.5 09°37’45,776”N 108°00’15,486”E

(CN TCTKVN – CTCP – BQLDAK Đông Nam Bộ supplied Coordinates above).

  1. M/V Nile River vessel ‘s Characteristics:

+ M/V Vessel: Nile River;

+ Call Sign: PEBF;

+ Dimension: 144,0m in length; 28,0m in width; 11,9m in Draught;

+ Color: Blue, White;

+ Nationality: Holland;

+ Số IMO: 9187007;

+ Signal in night time: Light marks as regulation

  1. Operation time: Expectation time for operation of M/V Nile River in Vũng Tàu waters: from 27/3/2020 to 11/9/2020 (about 6 months).

NAVIGATION GUIDANCE:

All vessels navigating on Vung Tau waters, should follow Notice to Mariners, pay attention to keep distance of M/V Nile River vessel with characteristics and coordinates position mentioned above, keep contact and absolutely comply with the Administration of Vung Tau for maritime safety.

For further information, please contact to: Branch of PV GAS-East-Southern Project Management Unit (PMU) Gas through Mr. Nguyen Huy Hoang Thang with mobile phone +84 908.571.888./.

SIGN ON BEHALF OF GENERAL DIRECTOR

DEPUTY GENERAL DIRECTOR

(Signed and Sealed)

Trần Đức Thi


Other notice

Continuing to establish the construction area of ​​the Sai Gon – Vung Tau fairway, Soai Rap (section in Hiep Phuoc) 2021

The sinking of the Tuan Tu 09 vessel in the waters of Binh Thuan province

Depth of waters in the water area in front of the wharf at the port is made of metal structure and petroleum equipment

(Vietnamese) Phương tiện thủy bị chìm trên luồng Sài Gòn – Vũng Tàu

The new establishment of AtoN buoys belongs to the project of Tan Thuan Wind Power Plant – Phase 1 and Phase 2, Ca Mau province