NOTICE TO MARINERS
Execution of Binh Khanh Bridge on Soai Rap River belongs to the North-South highway project, Ben Luc – Long Thanh section
No.21A/TBHH-TCTBĐATHHMN dated February 01, 2016
HCM – 14 – 2016
Waters: Ho Chi Minh City
Fairway: Soai Rap
Southern Vietnam Maritime Safety Corporation would like to inform: The execution of Binh Khanh Bridge on Soai Rap River belongs to the North-South highway project, Ben Luc – Long Thanh section, details as follows:
- Execution of driving P19 pile pier:
- Coordinates of pier center:
Point | VN-2000 | WGS-84 | ||
Latitude (j ) | Longitude (l ) | Latitude (j ) | Longitude (l ) | |
P19 | 10039’40,4” N | 106044’07,0” E | 10039’36,7” N | 106044’13,5” E |
- Range of execution area (in comparison with P19 pier center)
+ Towards upstream: 250m.
+ Towards downstream: 250m.
+ Towards fairway: 60m.
- Executed time: 28 months (Starting from January 26, 2016 to July 22, 2018)
- Execution of driving P20 pile pier:
- Coordinates of pier center:
Point | VN-2000 | WGS-84 | ||
Latitude (j ) | Longitude (l ) | Latitude (j ) | Longitude (l ) | |
P20 | 10039’36,4” N | 106044’18,7” E | 10039’32,7” N | 106044’25,2” E |
- Range of execution area (in comparison with P20 pier center)
+ Towards upstream: 250m.
+ Towards downstream: 250m.
+ Towards fairway: 60m.
- Executed time: 28 months (Starting from January 26, 2016 to July 22, 2018).
NAVIGATION GUIDANCE:
- All means navigating on Soai Rap fairway, pay attention to execution area mentioned above, strengthening guard and absolute compliance with appointing of regulation unit at the site for maritime safety.
Detail information or changes will be updated in next Notice to Mariners.