Notice to Mariners

The execution of “Dredging waters in front of Wharf section 1-7” construction works of PTSC Offshore Services

NOTICE TO MARINERS

The execution of “Dredging waters in front of Wharf section 1-7” construction works of PTSC Offshore Services

No. 220/TBHH-TCTBĐATHHMN dated September 28, 2022

VTU –  47 – 2022

Waters: Ba Ria-Vung Tau Province.

Fairway: Dinh River.

VMS-South would like to inform that the execution of “Dredging waters in front of Wharf section 1-7” construction works of PTSC Offshore Services, with the following details:

- The construction area limited by points below:

Points VN-2000 WGS-84
Latitude Longitude Latitude Longitude
N1 10023’29,6”N 107004’58,6”E 10023’25,9”N 107005’05,0”E
N2 10023’32,7”N 107004’49,9”E 10023’29,0”N 107004’56,3”E
N3 10023’37,3”N 107004’51,5”E 10023’33,6”N 107004’57,9”E
N4 10023’34,2”N 107005’00,3”E 10023’30,5”N 107005’06,7”E

- Construction time: it started on September 26, 2022, expected to be completed after 30 days from the date of commencement

- Construction means characteristics: Crane ships (Excavator), Liquid mud barges, Cutter suction and pump Dredger to Dumping ground for waste.

NAVIGATION GUIDANCE

All means navigating on Dinh River fairway, pay attention to reduce speed, keep watching and absolutely comply with the appointment of Maritime Administration of Vung Tau and the regulation force at the site for maritime safety./.


Other notice

(Vietnamese) Về việc tạm ngừng hoạt động của phao báo hiệu hàng hải số “4” luồng hàng hải Trần Đề.

(Vietnamese) Độ sâu vùng nước trước cảng CD trên sông Soài Rạp

(Vietnamese) Độ sâu khu neo đậu chuyển tải tại cửa biển sông Tắc – vịnh Nha Trang tỉnh Khánh Hòa

Depth of waters in front of wharf No.2, No.3 Sai Gon – Hiep Phuoc port

(Vietnamese) Thay đổi đặc tính ánh sáng Đèn biển Phước Mai