Notice to Mariners

The execution of “Dredging waters in front of Wharf section 1-7” construction works of PTSC Offshore Services

NOTICE TO MARINERS

The execution of “Dredging waters in front of Wharf section 1-7” construction works of PTSC Offshore Services

No. 220/TBHH-TCTBĐATHHMN dated September 28, 2022

VTU –  47 – 2022

Waters: Ba Ria-Vung Tau Province.

Fairway: Dinh River.

VMS-South would like to inform that the execution of “Dredging waters in front of Wharf section 1-7” construction works of PTSC Offshore Services, with the following details:

- The construction area limited by points below:

Points VN-2000 WGS-84
Latitude Longitude Latitude Longitude
N1 10023’29,6”N 107004’58,6”E 10023’25,9”N 107005’05,0”E
N2 10023’32,7”N 107004’49,9”E 10023’29,0”N 107004’56,3”E
N3 10023’37,3”N 107004’51,5”E 10023’33,6”N 107004’57,9”E
N4 10023’34,2”N 107005’00,3”E 10023’30,5”N 107005’06,7”E

- Construction time: it started on September 26, 2022, expected to be completed after 30 days from the date of commencement

- Construction means characteristics: Crane ships (Excavator), Liquid mud barges, Cutter suction and pump Dredger to Dumping ground for waste.

NAVIGATION GUIDANCE

All means navigating on Dinh River fairway, pay attention to reduce speed, keep watching and absolutely comply with the appointment of Maritime Administration of Vung Tau and the regulation force at the site for maritime safety./.


Other notice

32/TBHH-TCTBĐATHHMN – Depth of DongNai fairway

Depth of anchored area, avoid storms at Vũng Tàu – Thị Vải fairway was managed by the Administration of Vũng Tàu

Regarding the construction, maintenance and dredging of Soai Rap fairway

Pulling PVD III drilling rig from H17 position – Vung Tau Sea to Block 11-2/11

Depth of waters in Hyundai Vinashin shipyard